Engineering, Procurement, Construction — EPC
Commercial / Business
EPC, or Engineering, Procurement, Construction, is a turn-key contract model in which a single vendor takes full responsibility for three stages: technical design, component procurement, and construction through commissioning.
In Indonesia's solar PV (PLTS) sector, EPC contracts are used mainly for systems above 100 kWp — the client receives a system that is already operating rather than managing separate subcontractors [IRENA, Renewable Power Generation Costs, 2023].
The EPC scope of work is divided into three sequential phases. Engineering covers the site survey, system design (panel layout, inverter sizing, roof or ground-mount structure design), and preparation of technical specifications. Procurement is the sourcing of major materials — modules, inverters, cables, protection systems, and Balance of System (BOS) components — including price negotiation and logistics to the site. Construction covers physical installation, commissioning, testing, and handover of an operational system.
The client pays a single contracting point; the EPC vendor bears internal coordination across disciplines. The payment structure is generally either lump-sum (a fixed total price, with volume risk on the vendor) or cost-plus (reimbursement of actual costs plus a fee, with risk on the client). In Indonesia's B2B market, lump-sum is more common because it gives certainty on capital expenditure (CAPEX) for the buyer [LPJK, Construction Contract Guidelines, 2020].
An important distinction: EPC is a scope-of-work model, not a type of legal entity. A contractor is the company that executes; EPC describes what is being done. A single contractor can take on a non-EPC project (e.g. construction only, while the client handles engineering themselves).
Unlike the BOO and PPA schemes — where the vendor retains ownership of, or sells electricity from, the asset — under an EPC contract the PLTS asset becomes the client's property directly after handover. The client bears long-term operating costs but has no obligation to make recurring payments to the vendor once the project is complete.
Indonesian PLTS Application Example
A textile factory in Bandung with a 3,000 m² roof signs a lump-sum EPC contract for a 500 kWp PLTS system. The EPC vendor completes engineering (2D/3D design, roof load calculations), procurement (600 Wp TOPCon modules, two units of string inverter at 250 kWp each), and construction including commissioning and a production test. After handover, the factory owns the asset outright; estimated electricity bill savings are ~Rp 600-700 million per year based on the I-3 medium-voltage industrial tariff of Rp 1,114.74/kWh [PLN, tariff adjustment Q1 2026].
Sources & References
- IRENA, Renewable Power Generation Costs in 2023, International Renewable Energy Agency, 2024 (2024)
- LPJK (Construction Services Development Board), Standard Guidelines for Construction Contracts, 2020 (2020)
- Permen ESDM No. 5 Tahun 2017 — local content (TKDN) requirements for power generation projects, including utility-scale PLTS executed under EPC arrangements (2017)
See Also
PPA
(Power Purchase Agreement)PPA, or Power Purchase Agreement, is a long-term electricity sale-and-purchase agreement between a solar PV (PLTS) developer (developer/IPP) and an electricity user (off-taker), in which the off-taker pays a per-kWh tariff for the electricity consumed — rather than buying or owning the solar panel system.
BOO
(Build-Own-Operate)BOO, or Build-Own-Operate, is a solar PV (PLTS) financing scheme in which a developer builds, owns, and operates the installation on land or rooftop belonging to the tenant, while the tenant pays for electricity per kWh over the contract term — typically 10-25 years. There is no upfront capital outlay on the tenant's side.
BOS
(Balance of System)BOS, or Balance of System, is every component of a solar PV (PLTS) system other than the solar panels themselves: the inverter, mounting structure, DC and AC cabling, electrical protection, combiner box, export-import kWh meter, and installation labour. In an Indonesian residential on-grid system, BOS typically accounts for 25-40% of the total system cost.